Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/gakhpl/domains/gakhpl.com/public_html/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the twentytwentyone domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/gakhpl/domains/gakhpl.com/public_html/wp-includes/functions.php on line 6121
Highway Progress – Gakhpl
banner

Highway Progress

BRIEF of HIGHWAY PROGRESS in GENERAL (from Km 302+108 to 373+085)

Sr. No.

Description

Scope of Work Km. (4 Lane)

Work Complete Km. (4 Lane)

Remarks

1Clearing & Grubbing139.59137.58
2Sub-Grade139.59 133.06
3GSB139.59 131.88
4DLC135.996 127.86
5PQC139.59 122.19
6Subgrade (SR) 53.321 42.99
7GSB/CTSB(SR) 53.321 41.96
8WMM(SR) 53.321 29.18
9DBM(SR) 53.321 37.50
10BC(SR) 53.321 21.31