Physical Progress

Component % Weightage as per Schedule – G Physical Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road Works i/c Culverts, Minor Bridges, Underpasses & Approaches 64.45% 1.82% 55.69%
Major Bridge Works & ROB / RUB 3.14% 0.11% 2.00%
Structures [ Elevated Section | Reinforced Earth] 7.52% 0.48% 7.37%
Other Works 24.89% 1.41% 8.94%
Total 100.00% 3.82% 74.00%