| Component | % Weightage as per Schedule – G | Physical Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
| Road Works i/c Culverts, Minor Bridges, Underpasses & Approaches | 64.45% | 1.82% | 55.69% |
| Major Bridge Works & ROB / RUB | 3.14% | 0.11% | 2.00% |
| Structures [ Elevated Section | Reinforced Earth] | 7.52% | 0.48% | 7.37% |
| Other Works | 24.89% | 1.41% | 8.94% |
| Total | 100.00% | 3.82% | 74.00% |