Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/gakhpl/domains/gakhpl.com/public_html/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the twentytwentyone domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/gakhpl/domains/gakhpl.com/public_html/wp-includes/functions.php on line 6121
Service Progress – Gakhpl
banner

Service Progress

BRIEF of SERVICE ROAD PROGRESS in GENERAL (from Km 302+108 to 373+085)

Sr. No. Description Scope of Work Km. Work Commenced Km. Work Complete Km. Remarks
1 Sub-Grade 63.833 33.75
2 GSB 63.833 28.20
3 WMM 63.833 19.27
4 DBM 63.833 18.97
5 BC 63.833 1.24